Refer to the exhibit. An engineer must prevent the R6 loopback from getting into Area 2 and Area 3 from Area 0. Which action must the engineer take? A. Apply a filter list outbound on R3 and R7. B. Apply a filter list inbound on R2 and R9. C. Apply a filter list inbound on R3 and R7. D. Apply a filter list outbound on R7 only. Correct Answer: C This question is in 350-401 Implementing Cisco Enterprise Network Core Technologies (ENCOR) Exam exam For getting CCNP Enterprise Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by Cisco. Trademarks, certification & product names are used for reference only and belong to Cisco. The website does not contain actual questions and answers from Cisco's Certification Exam.