Refer to the exhibit. ROUTE.com is planning to implement EIGRP load balancing for traffic between hosts on the 172.16.10.0/24 and 172.16.20./24 networks. You have been asked to review the implementation plan for this project. Which statement about the plan is true? A. It is complete as written. B. It should include a task to configure multipath to equal a value of 2 on R1 and R4. C. It should use a ping instead of a traceroute to validate that load balancing has been activated. D. It should contain a task that documents the changes made to the configurations. Â Suggested Answer: A This question is in 300-101 Cisco Implementing Cisco IP Routing (ROUTE) Exam For getting Cisco Certified Network Professional (CCNP) Routing and Switching Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by Cisco. Trademarks, certification & product names are used for reference only and belong to Cisco. The website does not contain actual questions and answers from Cisco's Certification Exam.