Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

QuestionsCategory: CRISCSammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?
Admin Staff asked 6 months ago
Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

A. Sammy is correct, because she is the project manager.

B. Sammy is correct, because organizations can create risk scores for each objective of the project.

C. Harry is correct, the risk probability and impact matrix is the only approach to risk assessment.

D. Harry is correct, because the risk probability and impact considers all objectives of the project.








 

Suggested Answer: B

Sammy She certainly can create an assessment for a risk event for time cost, and scope. It is probable that a risk event may have an effect on just one or more objectives so an assessment of the objective is acceptable.
Incorrect Answers:
A: Just because Sammy is the project manager, it is not necessary that she is right.
C: Harry is incorrect as there are multiple approaches to risk assessment for a project
D: Harry's reasoning is flawed as each objective can be reviewed for the risk's impact rather than the total project.

This question is in CRISC exam 
For getting Risk and Information Systems Control Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to ISACA.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.