The customer's project manager changes during the final stage of a project. How can the project manager avoid a project closure delay? A. Update the stakeholder engagement plan B. Review the latest project status report and update the stakeholders C. Escalate the case to the customer's management team D. Issue the project payment invoice to the customer in advance Correct Answer: B This question is in PMP exam For getting PMP Certificate