The following findings are the result of an IS auditor’s post-implementation review of a newly implemented system. Which of the following findings is of GREATEST significance? A. The project’s 10% budget overrun was not reported to senior management. B. A lessons-learned session was never conducted. C. Measurable benefits were not defined. D. Monthly dashboards did not always contain deliverables. Suggested Answer: C Community Answer: C This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.
Please login or Register to submit your answer