The programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days. What should the project manager do? A. Evaluate the situation and identify ways to compress the schedule without impacting baselines. B. Ask the team to work overtime to complete the deliverable on time. C. Submit a change request to the project sponsor to change the schedule. D. Check the scope to verify if there is scope creep and get the project on schedule. Correct Answer: A This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer