The programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days. What should the project manager do?

QuestionsCategory: PMPThe programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days. What should the project manager do?
Admin Staff asked 1 year ago
The programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days.
What should the project manager do?

A. Evaluate the situation and identify ways to compress the schedule without impacting baselines.

B. Ask the team to work overtime to complete the deliverable on time.

C. Submit a change request to the project sponsor to change the schedule.

D. Check the scope to verify if there is scope creep and get the project on schedule.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.