The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project. If the project continues on the same path, it will consume twice the time and budget planned. What two actions can the project manager take to be more cost effective? (Choose two.) A. Conduct a stakeholder analysis B. Reinforce team communication. C. Update the project management plan with the new timeline D. Adopt an incremental approach E. Leverage work between team members Correct Answer: AD This question is in PMP exam For getting PMP Certificate