The project manager has observed that two team members have been arguing with each other openly at meetings. To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members. What two actions should project manager take? (Choose two.)

QuestionsCategory: PMPThe project manager has observed that two team members have been arguing with each other openly at meetings. To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members. What two actions should project manager take? (Choose two.)
Admin Staff asked 1 year ago
The project manager has observed that two team members have been arguing with each other openly at meetings. To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members.
What two actions should project manager take? (Choose two.)

A. Ask the team members to work it out themselves

B. Discuss this situation with other project managers and ask for advice

C. Reiterate ground rules at the next meeting and ensure that all team members are clear about these rules

D. Address the behavioral issue with each team member

E. Discuss the behavior directly with their managers and request them to correct the behavior CD








Correct Answer: CD

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.