The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources. What strategy should the project manager use in order to keep delivering value in a restricted environment?

QuestionsCategory: PMPThe project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources. What strategy should the project manager use in order to keep delivering value in a restricted environment?
Admin Staff asked 1 year ago
The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.
What strategy should the project manager use in order to keep delivering value in a restricted environment?

A. Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

B. Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance

C. Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and sta ng to account for those items

D. Restrict the project scope only to basic critical features and run the project with the current sta ng level until all of the budget is consumed C










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.