The risk found after a control has been fully implemented is called:

QuestionsCategory: 712-50The risk found after a control has been fully implemented is called:
Admin Staff asked 6 months ago
The risk found after a control has been fully implemented is called:

A. Total Risk

B. Transferred Risk

C. Residual Risk

D. Post Implementation Risk








 

Suggested Answer: C






This question is in 712-50 EC-Council Certified CISO (CCISO) Exam