The Salesforce development team is strictly following scrum to govern its releases. An executive trying to plan a vacation wants to know when work on the feature will begin so they can be available for additional implementation questions. After consulting with the product owner, the business analyst (BA) learns the team has decided to adopt Kanban instead for all future releases. What should the BA tell the executive? A. Work will begin after executive approval is given. B. Work will begin when capacity becomes available. C. Work will begin in the next sprint. Â Suggested Answer: B Community Answer: B This question is in Certified Business Analyst Exam For getting Salesforce Certified Business Analyst Disclaimers: The website is not related to, affiliated with, endorsed or authorized by Salesforce. Trademarks, certification & product names are used for reference only and belong to Salesforce. The website does not contain actual questions and answers from Salesforce's Certification Exams.