The sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders. What should the project manager do first? A. Determine which agile software tools will be required to support agile delivery within the organization B. Select a current predictive project, define the approach, and provide agile training to execute the remainder of the project C. Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted D. Determine how to transform the organization using agile techniques, including organizational training and communications Correct Answer: C This question is in PMP exam For getting PMP Certificate