The sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders. What should the project manager do first?

QuestionsCategory: PMPThe sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders. What should the project manager do first?
Admin Staff asked 1 year ago
The sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders.
What should the project manager do first?

A. Determine which agile software tools will be required to support agile delivery within the organization

B. Select a current predictive project, define the approach, and provide agile training to execute the remainder of the project

C. Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted

D. Determine how to transform the organization using agile techniques, including organizational training and communications










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.