There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

QuestionsCategory: CRISCThere are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?
Admin Staff asked 6 months ago
There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

A. Risk register

B. Work Performance Information

C. Project management plan

D. Change requests








 

Suggested Answer: D

Change requests are not one of the four inputs to the Risk Monitoring and Controlling Process. The four inputs are the risk register, the project management plan, work performance information, and performance reports.
Incorrect Answers:
A, B, C: These are the valid inputs to the Risk Monitoring and Controlling Process.

This question is in CRISC exam 
For getting Risk and Information Systems Control Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to ISACA.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.