Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed. Which three actions should the project manager do? (Choose three.)

QuestionsCategory: PMPThree testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed. Which three actions should the project manager do? (Choose three.)
Admin Staff asked 1 year ago
Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.
Which three actions should the project manager do? (Choose three.)

A. Stop the project and review the output.

B. Ask the testers to provide additional information.

C. Brainstorm the issue with the project team.

D. Continue with testing according to the plan.

E. Ask the sponsor for assistance and guidance.








Correct Answer: BCD

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.