Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations. What should the project manager do next to address this issue? A. Obtain and implement the sponsor's recommendations for a solution. B. Ask the team members to proceed independently while examining needs and alternatives. C. Place a hold on activities until the team can resume the work on-site. D. Halt all processes until procurement and implementation of solutions are completed. Correct Answer: B This question is in PMP exam For getting PMP Certificate