Two team members have had professional differences during the execution of a project, a situation that has impacted the performance of both members. Neither of them has wanted to talk to resolve their differences, even though the project manager has insisted on it. What technique should the project manager utilize next? A. Compromising B. Negotiating C. Smoothing D. Forcing Correct Answer: C This question is in PMP exam For getting PMP Certificate