Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before. How should the agile project leader resolve this situation? A. Update the project budget with the released team members. B. Update the restriction log with the new team capacity. C. Explain the new project requirements to the team. D. Explain the new team velocity to the customer. Correct Answer: D This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer