Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval. What should the project manager have done to prevent this from happening?

QuestionsCategory: PMPTwo weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval. What should the project manager have done to prevent this from happening?
Admin Staff asked 1 year ago
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval.
What should the project manager have done to prevent this from happening?

A. Sent the meeting minutes to the stakeholders after the kick-off meeting

B. Reviewed all the approvals immediately after the kick-off meeting was over

C. Ran separate kick-off meetings for each culture and time zone

D. Validated each stakeholder's understanding during the kick-off meeting










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.