What is one of the reasons a baseline might be changed? A. Numerous change requests B. To reduce redundancy C. Natural disaster D. Power fluctuation Suggested Answer: A Community Answer: A If the CMB is receiving numerous change requests to the point where the amount of requests would drop by modifying the baseline, then that is a good reason to change the baseline. None of the other reasons should involve the baseline at all. This question is in CCSP Certified Cloud Security Professional Exam For getting Certified Cloud Security Professional (CCSP) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISC. Trademarks, certification & product names are used for reference only and belong to ISC. The website does not contain actual questions and answers from ISC's Certification Exams.