When is the BEST time to identify risk associated with major projects to determine a mitigation plan? A. Project execution phase B. Project closing phase C. Project planning phase D. Project initiation phase Suggested Answer: C This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.