When it appears that a project risk is going to happen, what is this term called? A. Issue B. Contingency response C. Trigger D. Threshold Suggested Answer: C A trigger is a warning sign or a condition that a risk event is likely to occur within the project. Incorrect Answers: A: Issues are events that come about as a result of risk events. Risks become issues only after they have actually occurred. B: A contingency response is a pre-planned response for a risk event, such as a rollback plan. D: A threshold is a limit that the risk passes to actually become an issue in the project. This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.