QuestionsCategory: CRISCWhen it appears that a project risk is going to happen, what is this term called?
Admin Staff asked 6 months ago
When it appears that a project risk is going to happen, what is this term called?

A. Issue

B. Contingency response

C. Trigger

D. Threshold








 

Suggested Answer: C

A trigger is a warning sign or a condition that a risk event is likely to occur within the project.
Incorrect Answers:
A: Issues are events that come about as a result of risk events. Risks become issues only after they have actually occurred.
B: A contingency response is a pre-planned response for a risk event, such as a rollback plan.
D: A threshold is a limit that the risk passes to actually become an issue in the project.

This question is in CRISC exam 
For getting Risk and Information Systems Control Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to ISACA.

Next Post

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.