Which action must be performed before renumbering a Cisco UCS chassis?

QuestionsCategory: 350-601Which action must be performed before renumbering a Cisco UCS chassis?
Admin Staff asked 8 months ago
Which action must be performed before renumbering a Cisco UCS chassis?

A. Run the shut and no shut command on the connected ports.

B. Move the chassis to new ports on fabric interconnect.

C. Decommission the chassis.

D. Re-acknowledge the chassis.








 

Suggested Answer: C

Decommissioning is performed when a chassis is physically present and connected but you want to temporarily remove it from the Cisco UCS Manager configuration. Because it is expected that a decommissioned chassis will be eventually recommissioned, a portion of the chassis' information is retained by Cisco
UCS Manager for future use.
Renumbering a Chassis -
Before You Begin -
If you are swapping IDs between chassis, you must first decommission both chassis, then wait for the chassis decommission FSM to complete before proceeding with the renumbering steps.
Reference:
https://www.cisco.com/c/en/us/td/docs/unified_computing/ucs/sw/cli/config/guide/3-0/b_UCSM_CLI_User_Guide_3_0/
 b_UCSM_CLI_User_Guide_3_0_chapter_0100011.pdf

This question is in 350-601 DCCOR exam 
For getting CCNP Data Center Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by Cisco.
Trademarks, certification & product names are used for reference only and belong to Cisco.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.