Which component of ITIL pertains to planning, coordinating, executing, and validating changes and rollouts to production environments?

QuestionsCategory: CCSPWhich component of ITIL pertains to planning, coordinating, executing, and validating changes and rollouts to production environments?
Admin Staff asked 6 months ago
Which component of ITIL pertains to planning, coordinating, executing, and validating changes and rollouts to production environments?

A. Release management

B. Availability management

C. Problem management

D. Change management








 

Suggested Answer: A



Release management involves planning, coordinating, executing, and validating changes and rollouts to the production environment. Change management is a higher-level component than release management and also involves stakeholder and management approval, rather than specifically focusing the actual release itself. Availability management is focused on making sure system resources, processes, personnel, and toolsets are properly allocated and secured to meet SLA requirements. Problem management is focused on identifying and mitigating known problems and deficiencies before they occur.

This question is in CCSP Certified Cloud Security Professional Exam
For getting Certified Cloud Security Professional (CCSP) Certificate






Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISC. 
Trademarks, certification & product names are used for reference only and belong to ISC.
The website does not contain actual questions and answers from ISC's Certification Exams.
Question Tags:

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.