Which of the following correctly states the relationship between urgency, priority and impact?

QuestionsCategory: ITILFWhich of the following correctly states the relationship between urgency, priority and impact?
Admin Staff asked 1 year ago
Which of the following correctly states the relationship between urgency, priority and impact?

A. Impact, priority and urgency are independent of each other

B. Urgency should be based on impact and priority

C. Impact should be based on urgency and priority

D. Priority should be based on impact and urgency










Correct Answer: D