Which of the following correctly states the relationship between urgency, priority and impact? A. Impact, priority and urgency are independent of each other B. Urgency should be based on impact and priority C. Impact should be based on urgency and priority D. Priority should be based on impact and urgency Correct Answer: D This question is in ITIL Foundation exam For getting ITIL Foundation Certificate