Which of the following is a risk practitioner’s BEST recommendation to help reduce IT risk associated with scheduling overruns when starting a new application development project? A. Assign more developers to the project team. B. Involve the development team in planning. C. Implement a tool to track the development team’s deliverables. D. Review the software development life cycle. Suggested Answer: B This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.