Which of the following is MOST appropriate to add to a dashboard for the purpose of illustrating an organization's risk level to senior management? A. Results of risk and control testing B. Number of reported incidents C. Budget variance for information security D. Risk heat map Suggested Answer: D This question is in CISM exam For getting Certified Information Security Manager Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.