Which of the following is MOST helpful when prioritizing action plans for identified risk? A. Comparing risk rating against appetite B. Determining cost of controls to mitigate risk C. Obtaining input from business units D. Ranking the risk based on likelihood of occurrence Suggested Answer: A This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.