Which of the following is MOST helpful when prioritizing action plans for identified risk?

QuestionsCategory: CRISCWhich of the following is MOST helpful when prioritizing action plans for identified risk?
Admin Staff asked 6 months ago
Which of the following is MOST helpful when prioritizing action plans for identified risk?

A. Comparing risk rating against appetite

B. Determining cost of controls to mitigate risk

C. Obtaining input from business units

D. Ranking the risk based on likelihood of occurrence








 

Suggested Answer: A



This question is in CRISC exam 
For getting Risk and Information Systems Control Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to ISACA.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.