Which of the following is MOST important for an IS auditor to confirm during the implementation phase of a new system? A. Accuracy of error reports in recognizing erroneous data B. Whether system objectives and requirements were documented C. Whether appropriate internal controls are in place D. System parameters for scheduling and running the system  Suggested Answer: C Community Answer: C This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.