Which of the following is MOST important to update when an organization's risk appetite changes? A. Key risk indicators (KRIs) B. Risk taxonomy C. Key performance indicators (KPIs) D. Risk reporting methodology Suggested Answer: C This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.