Which of the following is MOST likely to require an organization to update its business continuity plan (BCP)? A. Successful BCP testing results B. Increases in information security risk trends C. Multiple changes in organizational leadership D. Major changes in the business operating environment Suggested Answer: D This question is in CISM exam For getting Certified Information Security Manager Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.