Which of the following is the BEST indicator of a successful project? A. it comes in at or below the expenditures planned for in the baseline budget B. it meets most of the specifications as outlined in the approved project definition C. it is completed on time or early as compared to the baseline project plan D. the deliverables are accepted by the key stakeholders  Suggested Answer: D This question is in 712-50 EC-Council Certified CISO (CCISO) Exam For getting EC-Council Certified CISO (CCISO) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by EC-Council. Trademarks, certification & product names are used for reference only and belong to EC-Council. The website does not contain actual questions and answers from EC-Council's Certification Exam.