Which of the following is the MOST appropriate indicator of change management effectiveness? A. Time lag between changes to the configuration and the update of records B. Number of system software changes C. Number of incidents resulting from changes D. Time lag between changes and updates of documentation materials Suggested Answer: C Community Answer: C This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.