Which of the following is the MOST cost-effective way to determine the effectiveness of a business continuity plan (BCP)? A. Stress test B. Tabletop exercise C. Full operational test D. Post-implementation review Suggested Answer: B Community Answer: B This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.