Which of the following is the MOST cost-effective way to test a business continuity plan? A. Conduct a tabletop exercise B. Conduct interviews with key stakeholders C. Conduct a disaster recovery exercise D. Conduct a full functional exercise Suggested Answer: A This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.