Which of the following is the PRIMARY concern when negotiating a contract for a hot site?

QuestionsCategory: CISAWhich of the following is the PRIMARY concern when negotiating a contract for a hot site?
Admin Staff asked 5 months ago
Which of the following is the PRIMARY concern when negotiating a contract for a hot site?

A. Complete testing of the recovery plan

B. Availability of the site in the event of multiple disaster declarations

C. Reciprocal agreements with other organizations

D. Coordination with the site staff in the event of multiple disaster declarations








 

Suggested Answer: B

Community Answer: B



This question is in CISA Certified Information Systems Auditor Exam
For getting Certified Information Systems Auditor (CISA) Certificate










Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA. 
Trademarks, certification & product names are used for reference only and belong to ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.