Which of the following items would commonly be on the agenda for a change advisory board (CAB)? 1. Details of failed changes 2. Updates to the change schedule 3. Reviews of completed changes

QuestionsCategory: ITILFWhich of the following items would commonly be on the agenda for a change advisory board (CAB)? 1. Details of failed changes 2. Updates to the change schedule 3. Reviews of completed changes
Admin Staff asked 1 year ago
Which of the following items would commonly be on the agenda for a change advisory board (CAB)?
1. Details of failed changes
2. Updates to the change schedule
3. Reviews of completed changes

A. All of the above

B. 1 and 2only

C. 2 and 3 only

D. 1 and 3 only










Correct Answer: A

This question is in ITIL Foundation exam
For getting ITIL Foundation Certificate