Which of the following provides the MOST comprehensive information when developing a risk profile for a system? A. Risk assessment results B. Key performance indicators (KPIs) C. A mapping of resources to business processes D. Results of a business impact analysis (BIA) Suggested Answer: C This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.