Which of the following should be the MOST important consideration when prioritizing the funding for competing IT projects? A. Skills and capabilities within the project management team B. Quality and accuracy of the IT project inventory C. Criteria used to determine the benefits of projects D. Senior management preferences Suggested Answer: C Community Answer: C This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.