Which of the following should be the PRIMARY input to determine risk tolerance? A. Risk management costs B. Annual loss expectancy (ALE) C. Regulatory requirements D. Organizational objectives Suggested Answer: D This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.