Which of the following statements is NOT true regarding the risk management plan? A. The risk management plan is an output of the Plan Risk Management process. B. The risk management plan is an input to all the remaining risk-planning processes. C. The risk management plan includes a description of the risk responses and triggers. D. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets. Â Suggested Answer: C The risk management plan details how risk management processes will be implemented, monitored, and controlled throughout the life of the project. The risk management plan does not include responses to risks or triggers. Responses to risks are documented in the risk register as part of the Plan Risk Responses process. Incorrect Answers: A, B, D: These all statements are true for risk management plan. The risk management plan details how risk management processes will be implemented, monitored, and controlled throughout the life of the project. It includes thresholds, scoring and interpretation methods, responsible parties, and budgets. It also acts as input to all the remaining risk-planning processes. This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.
Please login or Register to submit your answer