Which of the following tests is performed by an Information Systems (IS) auditor when a sample of programs is selected to determine if the source and object versions are the same? A. A substantive test of program library controls B. A compliance test of the program compiler controls C. A compliance test of program library controls D. A substantive test of the program compiler controls  Suggested Answer: C Community Answer: C This question is in 712-50 Certified CISO (CCISO) Exam For getting Certified CISO (CCISO) Disclaimers: The website is not related to, affiliated with, endorsed or authorized by EC-Council. Trademarks, certification & product names are used for reference only and belong to EC-Council. The website does not contain actual questions and answers from EC-Council's Certification Exams.