Which of the following would BEST determine whether a post-implementation review (PIR) performed by the project management office (PMO) was effective?

QuestionsCategory: CISAWhich of the following would BEST determine whether a post-implementation review (PIR) performed by the project management office (PMO) was effective?
Admin Staff asked 5 months ago
Which of the following would BEST determine whether a post-implementation review (PIR) performed by the project management office (PMO) was effective?

A. The review was performed by an external provider.

B. Management approved the PIR report.

C. Project outcomes have been realized.

D. Lessons learned were implemented.








 

Suggested Answer: C

Community Answer: C



This question is in CISA Certified Information Systems Auditor Exam
For getting Certified Information Systems Auditor (CISA) Certificate










Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA. 
Trademarks, certification & product names are used for reference only and belong to ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.