Which of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for completion of the actions 4. Complaints procedures

QuestionsCategory: ITILFWhich of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for completion of the actions 4. Complaints procedures
Admin Staff asked 10 months ago
Which of these should a change model include?
1. The steps that should be taken to handle the change
2. Responsibilities; who should do what, including escalation
3. Timescales and thresholds for completion of the actions
4. Complaints procedures

A. 1, 2 and 3 only

B. All of the above

C. 1 and 3 only

D. 2 and 4 only










Correct Answer: A

This question is in ITIL Foundation exam
For getting ITIL Foundation Certificate



Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.