Who should be responsible for determining which stakeholders need to be involved in the development of a risk scenario? A. Risk owner B. Control owner C. Compliance manager D. Risk practitioner Suggested Answer: A This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.