You are the project manager of HGT project. You are in the first phase of the risk response process and are doing following tasks : Communicating risk analysis results Reporting risk management activities and the state of compliance Interpreting independent risk assessment findings Identifying business opportunities Which of the following process are you performing?

QuestionsCategory: CRISCYou are the project manager of HGT project. You are in the first phase of the risk response process and are doing following tasks : Communicating risk analysis results Reporting risk management activities and the state of compliance Interpreting independent risk assessment findings Identifying business opportunities Which of the following process are you performing?
Admin Staff asked 6 months ago
You are the project manager of HGT project. You are in the first phase of the risk response process and are doing following tasks :
Communicating risk analysis results
Reporting risk management activities and the state of compliance
Interpreting independent risk assessment findings
Identifying business opportunities
Which of the following process are you performing?

A. Articulating risk

B. Mitigating risk

C. Tracking risk

D. Reporting risk








 

Suggested Answer: A

Articulating risk is the first phase in the risk response process to ensure that information on the true state of exposures and opportunities are made available in a timely manner and to the right people for appropriate response. Following are the tasks that are involved in articulating risk:
✑ Communicate risk analysis results.
✑ Report risk management activities and the state of compliance.
✑ Interpret independent risk assessment findings.
✑ Identify business opportunities.
Incorrect Answers:
B: Risk mitigation attempts to reduce the probability of a risk event and its impacts to an acceptable level. Risk mitigation can utilize various forms of control carefully integrated together. This comes under risk response process and is latter stage after articulating risk.
C: Tracking risk is the process of tracking the ongoing status of risk mitigation processes. This tracking ensures that the risk response strategy remains active and that proposed controls are implemented according to schedule.
D: This is not related to risk response process. It is a type of risk. Reporting risks are the risks that are caused due to wrong reporting which leads to bad decision.

This question is in CRISC exam 
For getting Risk and Information Systems Control Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to ISACA.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.