You are the project manager of the HGT project in Bluewell Inc. The project has an asset valued at $125,000 and is subjected to an exposure factor of 25 percent. What will be the Single Loss Expectancy of this project? A. $ 125,025 B. $ 31,250 C. $ 5,000 D. $ 3,125,000 Suggested Answer: B The Single Loss Expectancy (SLE) of this project will be $31,250. Single Loss Expectancy is a term related to Quantitative Risk Assessment. It can be defined as the monetary value expected from the occurrence of a risk on an asset. It is mathematically expressed as follows: Single Loss Expectancy (SLE) = Asset Value (AV) * Exposure Factor (EF) where the Exposure Factor represents the impact of the risk over the asset, or percentage of asset lost. As an example, if the Asset Value is reduced two third, the exposure factor value is .66. If the asset is completely lost, the Exposure Factor is 1.0. The result is a monetary value in the same unit as the Single Loss Expectancy is expressed. Therefore, SLE = Asset Value * Exposure Factor = 125,000 * 0.25 = $31,250 Incorrect Answers: A, C, D: These are not SLEs of this project. This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.
Please login or Register to submit your answer