You need to implement a backup solution for App1 after the application is moved. What should you create first?

QuestionsCategory: AZ-103You need to implement a backup solution for App1 after the application is moved. What should you create first?
Admin Staff asked 6 months ago
You need to implement a backup solution for App1 after the application is moved.
What should you create first?

A. a recovery plan

B. a Recovery Services vault

C. an Azure Backup Server

D. a backup policy








 

Suggested Answer: B

A Recovery Services vault is a logical container that stores the backup data for each protected resource, such as Azure VMs. When the backup job for a protected resource runs, it creates a recovery point inside the Recovery Services vault.
Scenario:
There are three application tiers, each with five virtual machines.
Move all the virtual machines for App1 to Azure.
Ensure that all the virtual machines for App1 are protected by backups.
References:
https://docs.microsoft.com/en-us/azure/backup/quick-backup-vm-portal

Implement and manage storage

This question is in AZ-103 Microsoft Azure Administrator Exam
For getting Microsoft Certified: Azure Administrator Associate Certificate



Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by Microsoft. 
The website does not contain actual questions and answers from Microsoft's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to Microsoft.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.