QuestionsCategory: CRISCYou work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?
Admin Staff asked 6 months ago
You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?

A. Data gathering and representation techniques

B. Expert judgment

C. Quantitative risk analysis and modeling techniques

D. Organizational process assets








 

Suggested Answer: D

Organizational process asset is not a tool and technique, but an input to the quantitative risk analysis process. Quantitative Risk Analysis is a process to assess the probability of achieving particular project objectives, to quantify the effect of risks on the whole project objective, and to prioritize the risks based on the impact to overall project risk. Quantitative Risk Analysis process analyzes the affect of a risk event deriving a numerical value. It also presents a quantitative approach to build decisions in the presence of uncertainty. The inputs for Quantitative Risk Analysis are:
✑ Organizational process assets
✑ Project Scope Statement
✑ Risk Management Plan
✑ Risk Register
Project Management Plan -
 <img src="https://www.examtopics.com/assets/media/exam-media/04284/0014500012.png" alt="Reference Image" />
Incorrect Answers:
A: Data gathering and representation technique is a tool and technique for the quantitative risk analysis process.
B: Expert judgment is a tool and technique for the quantitative risk analysis process.
C: Quantitative risk analysis and modeling techniques is a tool and technique for the quantitative risk analysis process.

This question is in CRISC exam 
For getting Risk and Information Systems Control Certificate


Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by ISACA.
The website does not contain actual questions and answers from ISACA's Certification Exams.
Trademarks, certification & product names are used for reference only and belong to ISACA.

Next Post

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.