Your company implements an Agile development methodology. You plan to implement retrospectives at the end of each sprint. Which three questions should you include? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point. A. Who performed well? B. Who should have performed better? C. What could have gone better? D. What went well? E. What should we try next?  Suggested Answer: BCE Sprint retrospective meetings - The sprint retrospective meeting typically occurs on the last day of the sprint, after the sprint review meeting. In this meeting, your team explores its execution of Scrum and what might need tweaking. Based on discussions, your team might decide to change one or more processes to improve its own effectiveness, productivity, quality, and satisfaction. This meeting and the resulting improvements are critical to the agile principle of self-organization. Look to address these areas during your team sprint retrospectives: ✑ Issues that affected your team's general effectiveness, productivity, and quality. ✑ Elements that impacted your team's overall satisfaction and project flow. ✑ What happened to cause incomplete backlog items? What actions will the team take to prevent these issues in the future? Reference: https://docs.microsoft.com/en-us/azure/devops/boards/sprints/best-practices-scrum This question is in AZ-400 Exam For getting Microsoft DevOps Engineer Expert Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by Microsoft. The website does not contain actual questions and answers from Microsoft's Certification Exams. Trademarks, certification & product names are used for reference only and belong to Microsoft.
Please login or Register to submit your answer